Over the next several weeks, the hydrogeologic consulting firm of Leggette, Brashears & Graham, Inc. (LBG) will be conducting pumping tests of two new MTUD’s wells. The work is being coordinated between MTUD, LBG, and the New Jersey Department of Environmental Protection (NJDEP).

 

We anticipate the pumping tests will take a minimum of 72-hours duration for each well.

 

The first pumping test will be conducted at new MTUD Well 26, located on Avenue K, and is expected to commence on April 25 and continue through April 29.

 

The second pumping test will be conducted at new MTUD Well 25, located on Spotswood-Englishtown Road just North of Texas Road, and is expected to commence on May 9 and continue through May 13.

 

If you have any questions about the testing program, please do not hesitate to contact Michael Barnes (MTUD Utility Director) or Michael Ott (MTUD Water Manager) at 732 521 1700 or Karen Benson/Frank Getchell of LBG at (201) 818-0700 x 128 or x 111, respectively.